1. Which is the highest organisational level in SAP
a) Plant b) Client c) Storage Location
Ans: b
2. For Material Master record PP Data which is the highest organisational level
a) Plant b) Client c) Storage Location
Ans: a
3. What is the difference between F1 Help & F4 Help.
a) F1 is for possible values and F4 is for application help b) F1 is for Application Help and F4 is for Technical Help c) F1 is for Field Help and F4 is for possible entries. d) None of the above
Ans: c
4. Variant Configuration is typically used in
a) Make – to – stock Environment b) Make – to – Order Environment c) Spare parts Sale d) Repetitive Manufacturing Environment
Ans: a
5. Configurable Material check for a material is set in _____________
a) Basic Data b) MRP View c) Sales View d) Classification
Ans:
6. Basic Data screen contains general data such as
a) Material Number b) Material description c) Base unit of measure d) Technical data
Ans: a, b, c
7. Functions of Classification are
a) To find an appropriate object b) To find similar objects c) To establish that no appropriate object exists.
Ans:
8. Entering “/o” in command field
a) Ends current transaction b) Ends the current cession c) Opens new cession d) Opens new transaction
Ans:
9. For creating Material Master the following Transaction Code is used :
a) md01 b) mm01 c) me01 d) mc01
Ans: b
10. The unit in which the stock keeping is done in a company is called
a) Stock unit of measure b) Base unit of measure c) Unit of issue d) Purchase unit of measure
Ans: b
11. Batch is
a) Same as material code b) Partial quantity of material managed separately from other quantity of same material in stock c) A non reproducible homogeneous unit with unique specifications d) None of above e) All of above
Ans: b
12. A _____________________________ is a complete, formally structured list of the components that make up a product or assembly.
Ans:
13. Component in the BOM are allocated to operation in
a) BOM b) Material Master c) Routing d) Work Center
Ans: c
14. BOM contains the following
a) List of Components b) Qty of Components c) Operation to which components is attached. d) Unit of Measure of components
Ans: a, b, d
15. BOMs are always created as
a) Single Level b) Multi Level c) Components d) Along with routings
Ans: a


What are the cutover activities followed for PP module?
I am listing some cut over activities to be followed (for PP - Discrete Manufacturing). Production Planning / Master data: For Production planning, only master data shall be migrated to SAP. In the 1st Stage, there is no master data. Following is the master data elements relevant for PP: - Bill of materials - Routing. - Work Centres. Transaction data: As of the cut off date, ideally there should not be any work in process. All the open production orders should be closed and semi finished goods should be dismantled and should be added to Raw materials. This strategy should be followed for all production orders where lead time to complete the production order is not large. Since, the production orders are for longer duration and it is not possible to dismantle the product and add it to inventory, following can be the strategy for migrating the data to SAP: - Create a material master for the work in process and set the standard price as the cost incurred for that product (ie. Work in process) - Create a bill of material (which will be used only for this production order) including this material and other materials still to be consumed. - Create Routing for rest of the production process. - Bring the work in process material into inventory as of the cut off date. - Create the production orders in SAP for the Work in process and issue materials to production order. Complete the production process after the cut off date of the project.

What happens to planned after it has been converted into production order?
When you convert Planned order to Production order. the planned order are offset by production order. Reference of planned order can be seen in the production order.

How to attach a drawing for a material to BOM? Is it possible?
Yes, you can attach a drawing. First create a document using Transaction Code "CV01N - Create Document". Attach your drawing in that document. The system will generate a document number. Assign this document in the BOM with item category D.
Report in Long Term Planning - You use long term planning for your customers, what they need are very simple, just to calculate future requirements for 1 or 2 years. Are there any reports in SAP to list of material requirement from LTP? You need a list of material requirement from long term planning result for each item.
Use MS70 then use MCEC.
Scheduling planned order -

How can you get planned orders scheduled so that you can do capacity leveling?

MD11 and then Schedule works fine but ideally you would want the the planned order scheduled automatically on creation? You have tried setting up an action to schedule the orders but cannot get that to work either.
When running MRP, try selecting "2" in the scheduling box this will bring planned orders into CM01 and CM21
Capacity planning CM01 - When you run capacity planning T-code: CM01, you found the plan orders are not included in the pegged requirement, you checked the profile, the check box for order and plan order are all actived.
Guess that planned orders have been created without capacity requirement indicator in MRP ("2" - Lead Time scheduling), if this is the case, then when converted to process orders they will have impact on the Resource. If you want to see them as planned orders, re-run the MRP or change in every planned order, going to the Menu: Edit --> Scheduling
Another couple of possibilities are to do with the routing/work centres used and whether it isactually calculates consumption of capacity of the category at the work centre being displayed in CM01 (it might consume a capacity pool or it might not consume the category).
MPS in Backgound/Online - You want to run MPS for a plant either online or in the background, but you do not get any results. If you run MPS for a single material/plant, then everything is 100% OK.
You need to run a planning file and a consistency check first, transaction OMDO and MDRE respectively you'll need to set up two jobs to do it but it is straight forward, once you've done this set up the background job for MPS to run and do it in NEUPL first time round and then change to NETCH after that.

What is the output of MPS run?
From MPS run you plan the materials which are of 'A' type in the abc analysis (80% dollar value) that have to be planned before hand. MPS is also a type of MRP only in which components just below the materials on which MPS run is taken place, are planned.
Table for production order status - What is the table for finding status (for Ex TECO ed prodn orders). We are not able to find from AFKO and AFRU tables the status of production orders or at least the link tables if known can be mentionned. You are unable to link the structure caufvd and IOHEADER WITH AFKO and AFRU.
JEST is the table.
Data dictonary table for SOP planning data - You are using Standard SOP (Info structure S076), in which table can you see the planning values that you maintained in MC93 transaction? You looked under table "S076" and did not see any values there.
Use T.Code MC95 to display your entries under the version which maintained the the table S076.
Production order operation's component allocation - How does SAP know that an operation has components as indicated by the component allocation indicator? Tcode CO08.
Component allocation is done via routing maintenance or BOM maintenance for the assembly. This is master data maintenance. As soon as a PO is created, the master data is read into the PO.
How to delete groups of products? How to delete a group of products that was created in screen MC84?
Delete the members in the product group and then archive the product group in transaction SARA, object=MM_MATNR. (The product group is created as a material master record with material type PROD and this record is deleted in SARA.)

What is the T-Code for trigger point?
CO30 MENUCO30 Standard trigger points CO31 SAPMCNSM Create standard trigger point CO32 SAPMCNSM Change standard trigger point CO33 SAPMCNSM Display standard trigger point
What the tcodes to archieve/delete a material BOM?
Look at this option to delete a material BOM There are two ways of deleting BOMs: - Using the Delete function. - Using the Deletion indicator.
If you select the deletion indicator, the BOM is archived in the next reorganization run, and can be deleted if required. In the BOM header, you set the indicator that controls physical deletion after the archiving run. You can still process the BOM within its validity period.This also applies if the deletion indicator is entered with reference to a change number with a valid-from date that is after the date of the next reorganization run
You can use the below mentioned tcodes:

CS25/CS28 Archiving for BOMs

CS26 BOM deletion

CS27 Retrieval of BOMs

Where shall we maintain number range for planned orders?
To maintain number range for planned order. Go to: MM-->CBP-->NUMBER RANGE-->DEFINE NUMBER RANGE FOR PLANNING RUN. Don't allow External Number Assignment.
What is t.code for planning calendar and factory calendar?
Planning Calendar--MD25 Factory Calender--SCAL

Menu Path

SPRO-->Materials Management-->Master Data-->Maintain Planning SPRO-->Calendar--md25
SPRO-->General Settings-->Currencies-->Expiring Currencies-->Maintain SPRO-->Calendar-->SCAL

20 comments:

  1. It was very nice article and very useful to SAP PP learners.
    thanks for sharing your knowledge. we also provide SAP PP Online Training by IT experts.

    ReplyDelete
  2. Good questions and answers with great pleasure, it's very useful can want for more information and free tutorials, demo can kindly visit.......

    Check this site Tekslate for in-depth sap pp Training
    Go here if you’re looking for information sap pp Training

    ReplyDelete
  3. Good questions and answers with great pleasure, it's very useful can want for more information and free tutorials, demo can kindly visit.......

    Check this site Tekslate for in-depth sap pp Training
    Go here if you’re looking for information sap pp Training

    ReplyDelete
  4. A debt of gratitude is in order for the inquiries and answers you posted on sap pp. For point by point data on sap pp Training visit our siteRead more... Free demo available.

    Check this site mindmajix for indepth Sap pp blogs.
    Go here if you’re looking for information on Sap pp training.

    ReplyDelete
  5. Thanks for sharing this Informative content. Well explained.Got to learn new things from your Blog.
    SAP MM

    ReplyDelete
  6. my friend Suggest me this blog and I can say this is the best blog to get the basic knowledge.Thank you so much for this sap hr abap online classes

    ReplyDelete
  7. Nice blog thanks for sharing the information
    SAP Tutorial

    ReplyDelete
  8. Good post..you have been put good efforts.thanks for sharing the valuable information. Best software Training institute in Bangalore

    ReplyDelete
  9. Hi,Thanks for sharing a Nice information it was nice to read this Blog. SAP PP Training in Irving

    ReplyDelete
  10. your blog is really useful for me. Thanks for sharing this useful blog..sap hr abap training

    ReplyDelete
  11. WOW! Really Nice Post! I personally believe that to maintain the standard of a blog all the hacks mentioned above are important. All points discussed were worth reading
    and I’ll surely work with them all one by one.

    CEH Training In Hyderbad

    ReplyDelete
  12. This comment has been removed by the author.

    ReplyDelete
  13. This comment has been removed by the author.

    ReplyDelete
  14. Hello admin,

    I am posting some slice over exercises to be pursued (for PP - Discrete Manufacturing). Generation Planning/Master information: For Production arranging, just ace information will be moved to SAP. In the first Stage, there is no ace information. Following is the ace information components important.

    Regards,
    Thanks

    RITU

    ReplyDelete
  15. Very nice post here thanks for it I always like and search such topics and everything connected to them.Excellent and very cool idea and the subject at the top of magnificence and I am happy to comment on this topic through which we address the idea of positive re like this.
    Salesforce Training in Chennai

    Salesforce Online Training in Chennai

    Salesforce Training in Bangalore

    Salesforce Training in Hyderabad

    Salesforce training in ameerpet

    Salesforce Training in Pune

    Salesforce Online Training

    Salesforce Training

    ReplyDelete
  16. I am looking for and I love to post a comment that "The content of your post is awesome" Great work!

    Data Analytics Training in Gurgaon

    ReplyDelete

Copyright SAP Production Planning | Using the GreenTech Theme | Bloggerized by Falcon Hive.com